Background: The Allen Bradley Site in Fairfield, New
Jersey is the former leased location of a specialty electronics manufacturing
facility. Rockwell International purchased Allen Bradley in 1985 and the site
was closed in 1994. Subsequently the site was converted into a school for
emotionally disturbed children. In September 1997 Rockwell retained an
environmental consulting firm, Vectre Corporation of Lafayette, New Jersey, to
review work performed by a previous consultant, and to advise Rockwell on what
actions were necessary to mitigate potential environmental hazards at the Allen
Bradley site.
Vectre conducted a detailed Remedial Investigation of the site
which suggested that septic wastewater injected into an on-site dry well had
produced TCE and DNAPL contamination in a plume about 20 feet below the surface
which threatened a nearby stream. They also concluded that the previous site
characterization had been inadequate, and that the natural attenuation and pump
and treat options previously considered would not satisfy Rockwell's desire to
expedite the site clean up. The existing database failed to adequately
characterize source areas, vertical concentration gradients, or health and
safety issues. After completing the investigation, Vectre concluded that a
permeable reactive barrier was both an appropriate technical solution and the
most responsive way to satisfy Rockwell's objective, which was to ensure that
the site was remediated in a timely and economical manner that satisfied all
health, safety and ecological issues.
Permeable Reactive Barrier Technology
Overview: Permeable Reactive Barriers are an effective, cost effective
method for the passive remediation of dissolved groundwater contamination. This
technology is gaining acceptance in the regulated community and is currently
deployed as full or pilot scale applications in over fifteen states. The
technology involves the placement of a reactive media into the subsurface where
it will intercept the flow path of a groundwater contaminant plume. Groundwater
is allowed to passively flow through the reactive media. As the contaminant
comes into contact with the reactive media it is degraded, precipitated or
sorbed. The design, monitoring and understanding of the reactions within the
system is critical to a successful application. Knowledge of the site-specific
conditions including a complete site characterization, determination of
subsurface geology and identification of a suitable reactive media are
necessary for deployment.
The ITRC formed the Permeable Reactive Barriers Team two years ago
when the technology became a priority among the ITRC states and federal
partners. During the first year the team developed a regulatory guidance
document entitled "Regulatory Guidance for Permeable Barrier Walls Designed to
Remediate Chlorinated Solvents" in addition to reviewing the US Air Force
Document entitled "Design Guidance for Application of Permeable Barriers to
Remediate Dissolved Chlorinated Solvents". Both documents have now been
finalized and distributed [to the ITRC participating states] for ITRC
consensus.
Remediation Review and Approval: Rockwell, Vectre and
the New Jersey Department of Environmental Protection (NJDEP) held a technical
meeting in Trenton on May 19, 1998 to discuss the Allen Bradley site. Prior to
the meeting, Matt Turner, an employee of NJDEP and also the ITRC Team Leader
for Permeable Reactive Barriers, provided the NJDEP attendees with copies of
the ITRC Guidance Documents. Attendees at this meeting included Mark Ishihara,
Rockwell project manager, Steve Tappert, the lead consultant for Vectre
Corporation, and Rob Lux and John Kosher from NJDEP. Rob Lux is the state
geologist for this site. John Kosher is the sire remediation Program Manager.
As background for the meeting Steve Tappert submitted an outline for a remedial
strategy which included excavation of the DNAPL and the use of a reactive wall
for containment and treatment of dissolved contamination. The type of reactive
wall they were considering was a "funnel and gate" system.
During the meeting the advantages and disadvantages of both funnel
and gate and continuous reactive walls were discussed. At that time the NJDEP
attendees offered Rockwell/Vectre the ITRC guidance documents as a resource to
assist in the decision process, design of the chosen system, and design of the
ground water monitoring program.
Steve Tappert was familiar with permeable reactive barrier
technologies, but had not previously done one himself. In Steve's own words:
"The initial meeting with the NJDEP in May resulted in my first introduction to
the ITRC documents. Recognizing that the NJDEP, through Matt Turner, had
participated in the development of the guidance documents I surmised that it
would be prudent to examine the documents closely and incorporate applicable
aspects to the project at hand."
In July 1998 Rockwell/Vectre submitted a Remedial Action Workplan
(RAW) to NJDEP which proposed excavation of the DNAPL area and back filling
with a mixture of reactive iron and sand. They proposed to address the
dissolved contamination using a continuous reactive wall 127 feet long, 5 feet
wide, and 16-25 feet deep. Verbal approval to construct the system was given by
the end of July. The review of the RAW was generally very straightforward for
several reasons: a very thorough soil and ground water investigation was
performed; there was favorable geology and distribution of the contaminants;
and the application of a technology, while technically complex in terms of
reactions and emplacement, was also fundamentally easy to understand and
visualize.
Summary of Benefits: Treatment of the DNAPL area and
installation of the continuous reactive wall were completed in mid-August 1998,
several weeks before school resumed at the site. Both Steve Tappert and Rob Lux
credit the ITRC Permeable Barrier Wall Regulatory and Design Guidance Documents
with significantly contributing to this expedited and successful site cleanup
process, as the following comments indicate.
Rob Lux, State Geologist: "It should be clear
that the key person in this case so far has been Steve Tappert of Vectre
Corp. He came to the Department with the proposal for a reactive wall and
addressed our concerns concerning source areas. His proposals were
straightforward and well documented. It was hoped that by supplying the ITRC
documents his job would be easier and that the Department would receive a high
quality product. Certainly the latter was true but I cannot speak to the
former."
Steve Tappert, Environmental Consultant: " Finishing
the job before school started was absolutely critical - the next window of
opportunity would have been the following summer, which may have allowed high
concentrations of contaminants to reach a major sewer interceptor in the
street. When we started the project there was considerable skepticism that it
could be completed within the allotted timeframe, and it took great cooperation
from NJDEP to do it."
"The whole process - design through installation - took less than
four months. That level of accelerated review is based upon a common pool of
knowledge provided in the ITRC documents. Some of the confidence behind that
[expedited] approach was due to the knowledge that our recommendation was
basically consistent with the ITRC documents. The design document was somewhat
useful in shifting our focus to a continuous wall rather than a funnel-and-gate
(which ultimately saved time during the review process and cost during
construction). I certainly used the monitoring design presented in those
documents because I had an added degree of confidence that the proposed program
would be accepted."
Mark Ishihara, Rockwell Program Manager "Rockwell
Automation's main objective for this site is to complete the remediation of the
groundwater in a timely and economical manner in order to satisfy the NJDEP,
the site owners, site tenants, neighbors and our stockholders. Additionally, we
needed to complete the installation of the remediation system before the start
of school this past fall. We were concerned that any delays in the approval of
our selected design system would prevent us from completing the installation in
time causing concerns for all our stakeholders and increasing the costs of the
system. With the cooperation of the NJDEP and VECTRE, we were able to meet this
installation objective."
Matt Turner, ITRC Permeable Barrier Team Leader
Permeable reactive barriers offer several advantages over conventional
technologies such as a pump and treat system. For instance, reactive barriers
are a passive in situ remedy with minimal operation and maintenance costs and
no energy requirements. While this technology has been deployed full scale at a
number of sites in the United States, it is still the subject of research and
technology verification projects.
Cost Comparison for Selected Remedy and Most Likely Alternative
Cost Element |
Reactive Wall
Per Year and Total |
Pump &
Treat Per Year and Total |
Cost Difference
Total |
Capital Cost |
$685,000 |
$350,000 |
$335,000 |
O&M,
Monitoring: |
1st Year |
90,000
90,000 |
250,000 250,000 |
-160,000 |
Year 2 -5 |
40,000 160,000 |
110,000
440,000 |
-280,000 |
Year 6-30 |
20,000
500,000 |
90,000 2,250,000 |
-1,750,000 |
Total Costs |
1,435,000 |
3,290,000 |
-1,855,000 |
Net Present value @ 7% Discount
rate |
$1,056,000 |
$1,670,000 |
$-614,000 |
The state review and approval process for the Allen Bradley site
took less than 3 months. This is the second site where NJDEP has approved use
of permeable reactive barrier technology. First use of this technology in New
Jersey was at the Caldwell Trucking CERCLA site in Fairfield, New Jersey, and
the review took about 15 months. First use of this technology in Massachusetts
(at a former manufactured gas plant) took over a year. The third use of this
technology in Colorado, took 10 months.
Site Name |
Site Location |
State Use |
Impact of ITRC Document Use
|
PBW Savings (NPV) Verses
Alternative |
Time to
Approve |
Salem Gas Plant |
Salem, MA |
1st |
Reduced overall state staff
review time 250 Hrs (50%) |
Not Available |
About 24 Months |
Caldwell Trucking |
Fairfield, NJ |
1st |
Reduced design review time
10% |
$10,000,000 |
About 15 Months |
Mound Plume |
Rocky Flats,CO |
3rd |
Reduced design review time
10% |
$2,700,000 |
10 Months |
Allen Bradley |
Fairfield, NJ |
2nd |
Avoided 1 year delay |
$ 614,000 |
3 Months |
This rapid and effective site remediation was of special
significance to the Gramon School. As the site tenant and therefore a major
stakeholder in the process they were anxious to assure that construction
activity at the site would not interfere with school operations.
David Weeks, Director of the Gramon School: " I was
aware that this was a relatively new technology and that Steve Tappert had
somehow been able to get it on a "fast track" with the regulators. I didn't at
all appreciate the high level of teamwork and cooperation that went into the
project until I read this study.
"Steve and Lee, his associate at Vectre, kept me regularly
informed of both the planning and the implementation of the project. Moreover,
whenever I appeared at the site, either one or the other was there at my side
to explain what was going on and to ask if I had any concerns.
"From our perspective, Steve's ability to plan and execute the
project on such a tight schedule was nothing short of miraculous! We were able
to open school on time in September without missing a beat. Rockwell
International must also receive high marks for its willingness to "go the extra
mile" in responding to our concerns both promptly and generously."
Who to Contact for Additional Information:
Marybeth P. Brenner, ITRC State Point-of-Contact New Jersey
Department of Environmental Protection 401 East State Street, POB 409
Trenton, NJ 08625 Phone: 609-292-6877 Fax: 609-292-7340 e-mail:
mbrennner@dep.state.nj.us
Rob Lux , Case Geologist New Jersey Department of
Environmental Protection 401 East State Street, POB 409 Trenton, NJ
08625 Phone: (609) 292-1998 e-mail:
rlux@dep.state.nj.us
Matt Turner, Permeable Reactive Barrier ITRC Team Leader New
Jersey Department of Environmental Protection 401 East State Street
Trenton, NJ 08625 Phone: 609-984-1742 Fax: 609-633-1454 e-mail:
mturner@dep.state.nj.us
Steve Tappert, Environmental Consultant Vectre Corporation
15 State Route 15 Lafayette, NJ 07848-2007 Phone: (973) 383-2500
Ext. 26 Fax: (973) 579-0025 e-mail: set@vectre.com
Mark Ishihara, Project Manager Rockwell Automation 1201 S.
Second Street Milwaukee, WI 53204 Phone: (414) 382-2566 e-mail:
mrishihara@ra.rockwell.com
Dr. David Weeks, Director The Gramon School 24 Dwight Pl.
Fairfield, NJ 07004-3304 Phone: 973-808-9555 Fax: 973-227-8626
e-mail: dweeks@idt.net |