Former Foreman's Cleaners, Salem, Oregon
Description
|
The former Foreman's drycleaners is located in a commercial/residential area in southeast Salem, Oregon. The property was a drycleaner from 1936 to 2001. Operations were discontinued in 2001, and the building was subsequently demolished. Stoddard solvent was used in the drycleaning until the mid-1980's, and PCE was used after that. Drycleaning equipment was located near an exterior door adjacent to the parking lot. Stoddard solvent was stored in a UST. Past spills of drycleaner solvent from equipment to the floor may have flowed out the door and into the gravel parking lot. Still bottom wastes were stored outside this door until 1982. A dry well was found during soil excavation activities. Chlorinated solvents were also found in the sanitary sewer lines.
Contaminant source areas were the UST area, drywell, and sanitary sewer lines. Remediation Status: In groundwater monitoring |
Contaminants
Contaminants present and the highest amount
detected in both soil and groundwater.
Contaminant | Media | Concentration (ppb) | Nondetect |
---|---|---|---|
sec-butylbenzene | groundwater | 278 ppb | |
sec-butylbenzene | soil | 7,500 ppb | |
chloroform | groundwater | 4.1 ppb | |
cis-1,2-Dichloroethene | groundwater | 70,000 ppb | |
cis-1,2-Dichloroethene | soil | 2,500 ppb | |
ethylbenzene | groundwater | 23.1 ppb | |
ethylbenzene | soil | 740 ppb | |
n-butylbenzene | groundwater | 159 ppb | |
n-butylbenzene | soil | 4,600 ppb | |
Tetrachloroethene (PCE) | groundwater | 136,000 ppb | |
Tetrachloroethene (PCE) | soil | 418,000 ppb | |
1,2,4-trimethylbenzene | groundwater | 1,450 ppb | |
1,2,4-trimethylbenzene | soil | 5,710 ppb | |
1,3,5-trimethylbenzene | groundwater | 430 ppb | |
1,3,5-trimethylbenzene | soil | 1,340 ppb | |
Trichloroethene (TCE) | groundwater | 36,300 ppb | |
Trichloroethene (TCE) | soil | 8,000 ppb | |
toluene | groundwater | 14.1 ppb | |
toluene | soil | 300 ppb | |
trans-1,2-Dichloroethene | groundwater | 720.4 ppb | |
trans-1,2-Dichloroethene | soil | 8,000 ppb |
Site Hydrology
Deepest Significant Groundwater Contamination: | 25ft bgs | |
Plume Size: | Plume Length: 180ft Plume Width: 100ft Plume Thickness: 55ft |
|
Average Depth to Groundwater: | 11ft |
Lithology and Subsurface Geology
Fill material Depth: 0-2ft bgs 2ft thick Gradient: 0.017ft/ft |
||
Gravelly silt Depth: 2-4ft bgs 2ft thick |
||
layers of clay and silty clay Depth: 4-61ft bgs 57ft thick |
Pathways and DNAPL Presence
Groundwater Sediments Soil DNAPL Present |
Remediation Scenario
Cleanup
Goals: |
PCE: 14,000 µg/kg |
Technologies
Ex Situ Soil Removal |
Why the technology was selected: Date implemented: Final remediation design: Results to date: Next Steps: Cost to Design and Implement: |
Costs
Cost
for Assessment: |
$150,000 | |
Cost
for Operation and Maintenance: |
Monitoring only @ $16,000/year | |
Total
Costs for Cleanup: |
Lessons Learned
1. Finding the dry well was unexpected and almost doubled the soil excavation and removal costs. |
Contacts
Nancy Sawka Oregon Department of Environmental Quality 750 Front St. N.E. Suite 120 Salem, Oregon 97301 |
Site Specific References
Focussed Site Investigation Report, June 15, 2000 Removal Assessment and Data Summary Report, April 16, 2001 |