State Coalition for Remediation of Drycleaners Site Profiles
Norge's Cleaners, Hays, Kansas
Description
|
The Former Norge’s Cleaners was identified as the source of a perchloroethylene (PCE) release that impacted PWS wells in 1984. The facility is located in a commercial district and the contaminant plume extends beneath residential and commercial areas. Kansas Dept. of Health and Environment (KDHE) also identified contamination resulting from two downgradient drycleaners: Former Royal T Drycleaner and Former Suburban Cleaners. KDHE treated the three areas as one site, because the PCE contaminant plumes commingled. KDHE conducted site investigations in 1994-1997 and began SVE remediation in 1997 and Dual Phase Extraction in 1999. A downgradient municipal packed tower air stripper system was also installed in 1999. |
Contaminants
Contaminants present and the highest amount
detected in both soil and groundwater.
Contaminant | Media | Concentration (ppb) | Nondetect |
---|---|---|---|
Tetrachloroethene (PCE) | groundwater | 3,500,000 ppb | |
Tetrachloroethene (PCE) | soil | 24,000 ppb | |
Trichloroethene (TCE) | groundwater | 15,000 ppb |
Site Hydrology
Deepest Significant Groundwater Contamination: | 50ft bgs | |
Plume Size: | Plume Length: 7,920ft Plume Width: 1,500ft |
|
Average Depth to Groundwater: | 48ft |
Lithology and Subsurface Geology
Silts and clays, with interbedded sand layers, 6 inches to 3 ft in thickness Depth: 0-35ft bgs 35ft thick Conductivity: 1.2ft/day Gradient: 0.052ft/ft |
||
Poorly sorted sand layer with fine to coarse gravel and caliche Depth: 35-40ft bgs 5ft thick |
||
silty clay Depth: 40-57ft bgs 17ft thick |
||
bedrock Depth: 57ft bgs |
Pathways and DNAPL Presence
Groundwater Sediments Soil DNAPL Present |
Remediation Scenario
Cleanup
Goals: |
Reduce PCE groundwater contamination to below MCL of 5 mg/L; reduce soil contamination below KDHE RSK level of 180 µg/kg. |
Technologies
In Situ Soil Vapor Extraction |
Why the technology was selected: Date implemented: Final remediation design: Results to date: Next Steps: Cost to Design and Implement: |
|
Ex Situ Air Stripping |
Why the technology was selected: Date implemented: Final remediation design: Results to date: Next Steps: Cost to Design and Implement: |
|
Ex Situ Pump and Treat |
Why the technology was selected: Date implemented: Final remediation design: Results to date: Next Steps: Cost to Design and Implement: |
Costs
Cost
for Assessment: |
$52,035 | |
Cost
for Operation and Maintenance: |
SVE only - $9,573 / 7 months; Dual Phase - $73,232 / 72 months | |
Total
Costs for Cleanup: |
Lessons Learned
1. Lowering of the water table allowed a much larger zone for SVE to remove soil gas vapors and greatly enhanced the SVE effectiveness. 2. Source area removal under buildings was extremely difficult to reach with SVE in silt/clays. 3. Jet pumps were used in extraction wells due to anticipated fines in the formation. Piping runs of 50-200 ft and did not work well with the jet pumps. The pumps tended to lose their prime, and as a result, lost pumping ability. 4. Improper contruction caused problems on certain well heads. Better oversight and installation could have prevented additional unneeded maintenance. 5. Sensaphone SCADA 3000 (a Supervisory Control and Data Acquisition system) was used at this site. This was one of the first SCADA 3000 units used in the field, and caused problems due to being located too close to the electrical panel. Electromagnetic fields generated from motor starters caused electrical disturbance which deleted SCADA programming. 6. Sequestering agent pump was not tied into the SCADA shut-down sequence. As a result, sequestering agent continued to pump following shut-down and plugged the piping and tray stripper. 7. Dual phase extraction system was very successful in the area influenced by the extraction wells. Additional wells are needed to capture additional source area. |
Contacts
Kansas Identified Sites List https://keap.kdhe.state.ks.us/BER_ISL/ISL_Pub_Detail.aspx?ProjectCode=C6 |